| |
Few obstacles
will present as big a challenge as concrete bowls. The
immense amount of sheer physical exertion needed on a pour day
should not be underestimated. When it came time to pour the
bowls, we contracted with a union concrete contractor to
provide us with six concrete finishers for three days. These
individuals were paid by the hour, with insurance and taxes
covered by the contractor. Expect to pay around $50 an hour.
These individuals were in addition to a team of five others
that had been involved in the construction (forming) up to
that point, and a few other volunteers cleaned the concrete
off tools and jigs. Just cleaning equipment is a full-time
job, but these volunteers can also assist in other ways
throughout the day. Overall, you will need a large team to
pour the concrete bowls.
We must mention a word or
two about union workers who do concrete finishing. First,
they will arrive with their own hand tools. Second, they will
arrive on time and be ready for work at 8 a.m. They will not
care if you are ready for them or not, and their time clocks
will be running. You can generally send the union labor home
within one hour without penalty (called on account of rain,
etc) except for a transportation fee. After one hour, they
will be paid for the first four hours regardless of the time
worked over that first hour. Likewise, after five hours of
work, they will be paid for eight hours. They are paid by the
hour for overtime by rounding up to the next hour. Overtime
is usually double (in our case $100 per hour). They will quit
promptly eight hours after start or expect overtime pay. Do
not expect them to stay around extra time without
compensation. They will not. So you want to time things
correctly so that they can complete all of the placement and
finishing within the eight hour period. Due to the nature of
concrete work, they will not take lunch, rather they eat as
they can throughout the day.
The upshot to this is that
union finishers are, in our experience, extremely
professional, especially if they come from a reputable
contractor and want to remain working for the company. It is
our experience that they will remain on the job for the full
day, no matter how difficult things get. Avoid the tendency
to just get a bunch of concrete workers together, even if they
are finishers, because pouring the bowls for a skatepark is
probably the most physically demanding work that any member of
the team has done in quite a while. It is not unforeseeable
that if you get some loosely knit crew that you will have some
walk-offs or no-shows the next day. For the pouring of bowls,
you want the best workers that you can find and the best may
cost more than usual. Do not scrimp on the labor needed to
pour the bowls.
For the St. Helens
skatepark, we planned to pour two bowls in three days. The
bowls were elongated ovals that were each 55 feet long and 38
feet wide. One bowl was 6 feet deep, the other was 8 feet
deep. There was a saddle in the center and a saddle at the
end where the small bowl connected to the street course.
Between the bowls and the surrounding deck, we needed 132
yards of concrete with a cost of over $5000 dollars a day
including labor and materials, but the results were well worth
it.
At six o’ clock a.m. on
the days of the pours, the team responsible for forming and
jigging should be at the site, making sure that the screeds
are in place, the rebar is blocked into the center of the
forms, and water hoses have been run and are ready. All
finishing tools should be gathered. In addition, it is a good
idea to have electric power available. Be as prepared as
possible for anything and everything. The pump truck should
be scheduled to arrive in time for set-up before the union
finishers arrive at 8 a.m. Contract with the pump truck
company well in advance as they are in high demand during peak
times. Try to get a little of the bill for the pump truck
donated. Work this angle well in advance of the pour. Expect
to pay around $1000 to $1500 a day for the rental of the pump
truck depending on the size of the truck.
So the pump truck is
there, and the finishers and the rest of the crew are
assembled. The first load of concrete should arrive at that
time and the driver should immediately begin preparations with
the pump truck driver. Specifically instruct the driver of
the concrete truck not to add any additional water to the
concrete mix without approval.
Now is the time to get
everyone, including all of the workers, together to discuss
how the bowl will be poured. With the St. Helens project,
none of the union finishers had ever done anything like this
before, with the exception of two that had some experience
with swimming pools. Remember, the finishers are there to do
whatever you tell them to do for the next eight hours. You
should be prepared to tell them when and where the pour will
begin and end, explain how the system works and answer their
questions. Overall, this meeting should take no more than
fifteen minutes.
The pour is then started
by pumping concrete a minimum of two-thirds of the way up the
bowl wall. Start up high, concrete doesn’t have any trouble
moving downward, but once placed it can only be moved higher
with a shovel. If the concrete is of the consistency
specified, it will start to stack upon itself up the sides of
the walls. Yet, there will be a lot of hand shoveling of
concrete to the top of the wall until it finally begins to
stay in place. When a section has been filled from top to
bottom, the screed is dragged across (see previous sections).
When constructing a bowl this requires one worker at the top,
one at the bottom and one working in the center of the
screed. At this point, some workers will remain to float that
section while others working with the screed move ahead.
Eventually workers will begin to finish and trowel the area
where the pour started and the crew will be dispersed among
the various stations of placing, floating, finishing and
troweling.
One person will walk
around the inside and outside of the bowl determining where
high and low spots exist that must be refinished. There must
be someone that is responsible for saying “O.K. This is good
enough, time to move on.” For you to have the highest quality
skatepark possible, this individual must understand the entire
process from start to finish and be attentive to detail. He
or she must not be afraid to insist on perfection and demand
that others insist upon it as well. This person should be
familiar with what makes and breaks it when building a
skatepark. Chances are this person will all ready have
identified themselves by their dedication to the project up to
this point. Choose this person carefully.
The rate at which
additional concrete trucks are ordered must be determined
during the pour. Do not get ahead of yourself with the
concrete. It is much better to get the concrete that is all
ready placed finished properly than to place more concrete
than you can finish just because it is there. If you have to,
send the truck with the concrete back. If it is your fault
you will still have to pay for it, but you will be able to
maintain the quality of the park.
RETURN TO CONTENTS
|
|